Advanced Tailings Dam Breach Analysis Using the Material Point Method

MPoint3D

MPoint3D

ITASCA Software Partner: Geosyntec Mining (formerly Red Earth Engineering)

Partner Role: Industry Beta Test Partner in MPoint Development

Project Team: Nicolas Pereira, Senior Geotechnical Engineer, and Sudheer Prabhu, Geotechnical Engineer

Software Used: MPoint3D

Overview

Accurate development of hydrographs that estimate breach evolution, discharge rates, and released volumes is one of the most important aspects of tailings dam breach analysis. Traditional approaches for breach parameter estimation are developed based on water dams, which tend to be conservative and do not adequately represent the complex failure mechanisms and flow behavior associated with tailings storage facilities (TSFs).

To address this challenge, Geosyntec Mining applied the Material Point Method (MPM) using ITASCA’s MPoint software to simulate the Brumadinho tailings dam failure that occurred in Brazil in 2019. The work was undertaken as part of Geosyntec Mining’s role as an industry beta test partner for MPoint, giving the team extended experience with the software ahead of its commercial release. Nicolas Pereira and Sudheer Prabhu carried out the Brumadinho tailings dam breach modeling, along with the associated research and case study (Pereira et al., 2026).

The Brumadinho failure caused extensive damage and the loss of more than 270 lives. The failure involved flow liquefaction that led to a mudflow event that released a volume of around 9.7 Mm3, the majority of which occurred within 5 minutes of the initial failure.

This case study examines the failure to demonstrate how advanced numerical modeling using the innovative MPM approach can provide a more traceable, physics-based approach to develop breach outflow hydrographs to support consequence assessment and emergency planning of tailings storage facilities.

The Challenge

To develop breach outflow hydrographs for tailings dam breach analysis, engineers traditionally define breach geometry and related parameters based on empirical equations developed from water dam failures. Tailings dams, however, have a higher concentration of solids, and failure progression is controlled by non-Newtonian flow behavior, meaning this approach can introduce significant uncertainty by misrepresenting outflow dynamics.

To comply with standards and recommendations from the Global Industry Standard on Tailings Management (GISTM), the Canadian Dam Association (CDA), and the International Commission of Large Dams (ICOLD), operators need more defensible approaches that accurately represent geotechnical conditions and failure mechanisms specific to TSFs. This study contributes to this aim through a numerical modeling approach for tailings dam breach analysis based on traceable, physics-based methodology as opposed to the current practice based on empirical methods.

The Solution

Geosyntec Mining developed a three-dimensional numerical model of Dam I of the Brumadinho tailings facility using ITASCA’s MPoint3D software, which combines the Finite Difference Method (FDM) and the Material Point Method (MPM) within a single computational framework.

The model incorporated detailed dam geometry and topography, water table data, and in-situ stress conditions. The Mohr-Coulomb constitutive model was applied for all materials. The goal of this model was to capture post-failure runout dynamics, not failure initiation, so all materials are assumed to have residual liquefied shear strength to represent their post-liquefaction state.

Discharge and mobilized volume emerged from the simulated geomechanical response of the tailings and embankment materials to develop the breach outflow hydrograph.

Isometric view of MPoint model of the base case at different time intervals. Top row illustrates material distribution; bottom row illustrates velocity contours.

Why the Material Point Method?

The Material Point Method, which is the foundation of MPoint, is particularly well suited for extreme deformation problems involving material failure, liquefaction, runout analysis, and post-failure material movement: all key elements of tailings dam breach analysis. In fact, the National Academies of Sciences has recognized the application of MPM in dam breach and failure assessments as an advancement to traditional modeling methods (NASEM, 2021).

In MPM, moveable material points carry stress, strain, density, and strength information and are mapped on a temporary background grid each step to compute stresses and strains. This approach enables continuous simulation of large deformation without the mesh distortion issues that often halt simulation in traditional numerical methods.

MPoint can simulate breach initiation, progression of failure, and downstream material release within a single model, providing a streamlined framework for failure analysis of complex systems like tailings storage facilities.

Results

The MPM simulation successfully reproduced key characteristics of the Brumadinho failure, including the rapid loss of stability, progression of large deformation, and flow of the liquefied tailings. The breach hydrograph can then be developed directly from the evolving mechanics of the failure process rather than from assigned breach parameters as in traditional methods, which improves traceability to increase confidence in the analysis.

The base-case model predicted:

A comparison of the hydrographs developed from this study and a study by Lumbroso et al. (2021), which was based on data calibrated to match the reported characteristics of the failure, highlights the differences in the two modeling approaches. In this study, the estimated peak discharge was 48% higher than in the calibrated hydrograph, followed by a rapid decline, indicating that the bulk of mobilized material quickly exited the TSF, matching the observed timing of failure.

Comparison of breach outflow hydrographs of the base case in this study (red line) and hydrograph calibrated in a study by Lumbroso et al. (2021) (dashed black line).

Sensitivity Analysis

Additional simulations evaluated the effect of residual undrained shear strength ratios on breach behavior. Sensitivity studies with values ranging from 0.01 to 0.06 showed that decreasing residual strength significantly affects breach severity through increased peak discharge and mobilized volume. Meanwhile, the timing of peak discharge and initial velocity remained relatively consistent across cases, indicating that the geometry of the facility and gravitational forces are the controlling factors.

The MPM approach used in this study provides results that are based on the large-deformation physics governing the failure that are directly traceable to geotechnical characterization of the site, rather than calibrated data. The methodology improves reliability in tailings dam breach assessments and consequence evaluations, providing valuable information for emergency preparedness.

Breach outflow hydrographs for different values of residual undrained shear strength ratios over 90 seconds of simulation.

Benefits of the Material Point Method Approach

By leveraging ITASCA’s MPM software MPoint, Geosyntec Mining developed a workflow that:

Looking Forward

As regulators and operators place greater emphasis on tailings dam safety and risk management, advanced numerical methods are becoming increasingly important tools for understanding breach behavior. The Brumadinho case study demonstrates how Material Point Method software like MPoint can provide a credible, physics-based alternative to conventional breach hydrograph estimation methods while offering deeper insight into the mechanics governing large-scale tailings failures.

MPoint let us simulate breach initiation and runout in a single framework, so the hydrograph comes out of the mechanics of the failure rather than an empirical assumption. For our clients, that means a breach analysis they can trace back to the geotechnical characterisation of their facility.

Nicolas Pereira, Senior Geotechnical Engineer, and Sudheer Prabhu, Geotechnical Engineer, Geosyntec Mining

About Geosyntec Mining

Geosyntec Mining is a specialist tailings and dam engineering consultancy with offices in Australia. The team provides tailings storage facility design, dam breach and consequence assessment, Engineer of Record services, and advanced numerical modelling to mining clients in Australia and internationally. Learn more at https://geosyntec.com.au/.

References

×